Stirley Farm EnerPHit – supporting the external walls

Barn at Stirley Community Farm - before retrofit

Barn at Stirley Community Farm – before retrofit

At the beginning of our Stirley Community Farm EnerPHit project, we commissioned a structural survey, which unfortunately revealed that there is lot of work needed to stabilise the walls and to underpin the foundations, because the foundation aren’t deep enough. To address this problem, the timber frame structure we are proposing will have a dual function: offering excellent levels of airtightness and insulation, while also serving to support and shore up the original stone building.

 

 

 

 

 

Wall connectors

 
Stirley Farm EnerPHit: concrete wall connectors detail

Stirley Farm EnerPHit: concrete wall connectors detail

Stirley Community Farm EnerPHit: positioning concrete wall connectors into the wall

Stirley Community Farm EnerPHit: positioning concrete wall connectors into the wall

The inner frame will brace the original barn fabric through a purpose designed tie system we have developed with our structural engineers.  Concrete pads will be cast into the original stone walls at intervals and these will be tied to the frame via stainless steel* (*changed to Teplo Ties later on in the build) threaded bars set in resin anchors into the cast blocks. The additional challenge has been to avoid a cold bridge, so the bolted connection to the I beam structure has had to be carefully detailed to ensure that this connection is fully insulated.

 

On site

We are currently preparing the site for the building work proper to begin. We have been demolishing a roofless brick wall extension attached to the barn. All usable building rubble is being recycled/ re-used elsewhere on the site.  The barn’s  (asbestos) roof has been removed and the cow stalls within the barn taken down.  The team have started positioning the concrete ‘wall connectors’ (mentioned above) into the wall. In the next blog, we’ll address ways in which we are tackling underpinning and tanking issues in the ground floor.

Bill Butcher, Director, Green Building Store www.greenbuildingstore.co.uk

Free resources on the project are available at: www.greenbuildingstore.co.uk/enerphit

15th October 2012

2 responses to “Stirley Farm EnerPHit – supporting the external walls”

  1. blank Seamus Sheehy says:

    Did you carry out a Wufi Analysis of the proposed wall structure. If you did can you supply the details. Thanks

    • Good question! We are planning to have Wufi analysis on the project when all the fine details have been resolved. We will, of course, share this on the blog when it is ready.
      Bill

Leave a Reply

Your email address will not be published. Required fields are marked *

Affiliations & Accreditations